You don't have javascript enabled. Good luck with that.
Pencarian
Jalan Layang Ciledug-Tendean Rampung 17 Persen

CIledug-Tendean Flyover Project 17 Percent Complete

The construction of a flyover for Transjakarta bus lane plying corridor XII (Ciledug-Kapten P Tendean) has reached 17 percent. It is beyond determined target that was about 14 percent. 

Currently, it's been 17 percent, and beyond our target that was 14 percent

The project is divided into 8 packets. The construction of the 9,3-kilometer flyover would take 661 days starting from February 2015 and targeted to be complete in December 2016. 

"Currently, it's been 17 percent, and beyond our target that was 14 percent," said Head of Jakarta Bina Marga's Overpass and Intersection Department, Heru Suwondo, Tuesday (8/11). 

Congestion Along Ciledug-Tendean Getting Worse

Regarding traffic congestion caused by the project, Suwondo claimed, he will try maximally to anticipate it by coordinating with police and Jakarta Transportation Department. 

He also promises to re-function damaged roads and sidewalks due to the project, as before. 

"The roads and sidewalks will eventually be functioned as before. For instance, if there are formerly 2 lanes, they would keep being like that, as well as sidewalks for pedestrians," he explained.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2359 personDessy Suciati
  2. Immersive Room and Glowing Forest Attractions Enliven Eid at TMII

    access_time26-03-2026 remove_red_eye1000 personFakhrizal Fakhri
  3. Deputy Governor Watches Pelangi di Mars with Orphans

    access_time27-03-2026 remove_red_eye834 personTiyo Surya Sakti
  4. 292 East Jakarta Personnel Mobilized for Eid Return Rush

    access_time25-03-2026 remove_red_eye777 personNurito
  5. Jakarta's Mudik to Jakarta Program Hits Rp21 Trillion in Transactions

    access_time25-03-2026 remove_red_eye759 personFakhrizal Fakhri