Jalan Layang Ciledug-Tendean Rampung 17 Persen
.
photo istimewa - Beritajakarta.id

CIledug-Tendean Flyover Project 17 Percent Complete

The construction of a flyover for Transjakarta bus lane plying corridor XII (Ciledug-Kapten P Tendean) has reached 17 percent. It is beyond determined target that was about 14 percent. 

Currently, it's been 17 percent, and beyond our target that was 14 percent

The project is divided into 8 packets. The construction of the 9,3-kilometer flyover would take 661 days starting from February 2015 and targeted to be complete in December 2016. 

"Currently, it's been 17 percent, and beyond our target that was 14 percent," said Head of Jakarta Bina Marga's Overpass and Intersection Department, Heru Suwondo, Tuesday (8/11). 

Congestion Along Ciledug-Tendean Getting Worse

Regarding traffic congestion caused by the project, Suwondo claimed, he will try maximally to anticipate it by coordinating with police and Jakarta Transportation Department. 

He also promises to re-function damaged roads and sidewalks due to the project, as before. 

"The roads and sidewalks will eventually be functioned as before. For instance, if there are formerly 2 lanes, they would keep being like that, as well as sidewalks for pedestrians," he explained.

Linked News
Popular News indeks
  1. Long Holidays will Be More Exciting with Rawa Belong Bandeng Festival

    access_time25-01-2025 remove_red_eye663 personAldi Geri Lumban Tobing
  2. Chinatown Festival Enlivens Lunar New Year Celebration at TMII

    access_time25-01-2025 remove_red_eye605 personNurito
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye520 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye491 personDessy Suciati
  5. Rain Brings Excitement to Rawa Belong Milkfish Festival 2025

    access_time28-01-2025 remove_red_eye394 personFolmer